icon-cross
Map

Energy from Waste Facility

Jersey

The new Energy From Waste Facility forms part of Jersey's Solid Waste Strategy, which includes the minimisation of waste production through reusing and recycling before waste is offered for energy extraction and disposal. EPR was appointed to provide the detailed design of the envelope and office accommodation block for the Energy From Waste and ancillary (bulk waste and ash handling) buildings. The result is a site that is uncluttered and a building with a clear architectural concept delivered with quality in the materials and detailing without compromise to the efficient design and operation of the plant itself.

Download
Jerseywaste Rocks

Jersey has used Energy From Waste technology since the commissioning of the site at Bellozanne in 1979, processing 80,000 tonnes per year of the island’s inert, solid waste until it reached the end of its life and was unable to reliably serve the island. 

The technology employed at the Bellozanne site had been outstripped by modern, contemporary facilities. The States of Jersey rigorously tested its Solid Waste Strategy and subsequently concluded that a new 120,000-tonne-per-year Energy From Waste facility at La Collette would replace the Bellozanne plant.

For the OJEU bid submission, Camerons entered into a consortium with Spie Batignolles as civil engineers and CNIM as technical installation designers and contractors. The CSBC consortium achieved preferred bidder status in May 2008 and entered into contract with The States of Jersey in November 2008 for the delivery of the completed building. Works commenced on site in January 2009 and were completed at the beginning of 2011.

The States of Jersey employed a consultant architect to obtain planning approval for the concept design, and EPR was closely involved in the detailed design development of that concept scheme prior to planning.

EPR was responsible for the detailed design of the building through the construction phase in accordance with the Architectural Criteria established by the planning consent and included in the Employer’s Requirements. As with all Energy From Waste facilities, developers and operators were mindful of the environmental cost of transportation of waste from the point of collection to the plant.The principles of proximity therefore suggested that they should be located as closely as possible to the waste’s point of origin, which means near commercial or residential areas. This requires that such plants achieve a high degree of architectural quality given the visual impact in any environment. 

EPR’s approach preserved the quality of the concept design by working very closely with the construction team and the technical installation design. Whilst understanding and respecting the scale and complexity of the process operation, we collaborated to carefully control the size and location of penetrations through the façades (louvers, ducts  flues etc) and ancillary external elements (silos, tanks, weigh-bridges etc). The result is a site that is uncluttered and a building with a clear architectural concept delivered with quality in the materials and detailing without compromise to the efficient design and operation of the plant itself.

Jerseywaste Section
Jerseywaste Window
Jerseywaste Roof

The design team included structural engineers, services and acoustic consultants and landscape designers. Wider consultation on the project addressed fire safety, sustainability strategy and the various aspects of Environmental Impact. EPR was central to the co-ordination of these parties, as well as the interface with the building’s civil engineering and technical installation.

It was necessary to gain some understanding of the technical process in order to successfully co-ordinate the design team and respect the complexity of the design within the building envelope. This was achieved through visits to plants in the UK and Europe that are either operational or under construction. The team regularly met either around the table, or via video conference to ensure programme integration and design co-ordination.

Jerseywaste Dusk
Jerseywaste Detail
Jerseywaste Construction

EPR’s approach to this new sector was to observe, listen and understand the requirements of the client, the operator and the local community. Through this we have gained an understanding of both the technical requirements of the plant’s design and operation, and the sensitivities of residents and business that surround the site. This has informed our strategy to deliver a building of high architectural quality that will serve Jersey’s waste and energy needs for many years to come.

Client: States of Jersey | Services: Architecture | Size: 5,535m²